  • 怎样搭建活动板房?
  • 本站编辑:杭州劳宇集装箱移动板房有限公司发布日期:2018-03-12 16:23 浏览次数:

一、施工流程

1. Construction process


放线——挖基槽——C15砼基础地梁及地面混凝土垫层施工——地梁安装——立柱安装——楼面一字梁系统安装——走道系统安装——外墙板安装——窗安装——门安装——雨棚系统安装——屋面系统安装——内隔墙板安装——PVC吊顶——清洁现场——竣工验收

On line C15 concrete foundation trench excavation and concrete beam ground cushion construction - beam - column installation Installation - floor beam system installation - word walkway system installation - wall panel installation - window installation - door installation, system installation, installation of canopy roof system, partition board installation, PVC ceiling cleaning, scene completion acceptance


二、施工要点

Two. The main points of construction


调整地梁标高时,同一地梁两端±5MM,跨间控制在±10MM。地梁与墙面板间应加装防水槽,并且防水槽间用玻璃胶封闭,以防漏水。立柱安装垂直度用磁力线坠测量,偏差控制在L/100内,且≤10MM。走道板间空隙用玻璃胶填缝。屋面板间接缝用密封胶封堵。

When the elevation of the ground beam is adjusted, the two ends of the same ground beam are + 5MM, and the inter span control is within + 10MM. The water proof tank should be added between the ground beam and the wall panel, and the waterproofing tank is sealed with glass glue to prevent water leakage. Install the column verticality with the flux drop measurement, deviation control in L / 100, and less than 10MM. The gap between the aisle plates is filled with glass sealant. The indirect sealant of the roof panel is blocked by sealant.


三、施工要求

Three. Construction requirements


1)钢结构

1) steel structure


各构件安装位置应符合设计要求,现场焊接部件位应准确,无假焊、漏焊。

The installation position of each component should be in accordance with the design requirements. The site welding parts should be accurate, without false welding and leakage welding.


2)紧固件

2) fastener


a、紧固件应符合GB5782规定

A and fasteners should be in accordance with GB5782


b、螺栓必须按设计要求的规定,位置安装正确并垫好垫圈,不得少装、漏装。

B, bolts must be set according to the requirements of the design, the position is installed correctly and cushion washer, must not be installed, leaking.


C、构件间的连接螺栓必须要拧紧。

C, the connecting bolts between the components must be tightened.


3)油漆

3) paint


a、经现场焊接及运输途中底漆剥落处应重刷防锈漆一层

A, spot welding and transportation of primer should be repainted one layer of antirust paint


b、构件露明部位刷面漆二层,油漆不得有漏刷、脱皮、挂漆及返锈现象。

B, component parts having two layers of paint brush paint, no leakage of brush, peeling, hanging paint and rust phenomenon.


4)墙体

4) wall


a、按排板图将夹芯彩钢板、墙面必须校正,伞墙的转角处及阳角处用角铝封口,板与板之间连接采用工字铝连接,各墙须垂直,嵌缝深度一致,整齐清洁,墙面应清洁,颜色一致,板缝齐整,铆钉采用Φ5X13@300,打钉面上下要一致,不得有错落,必要部位采用自攻螺栓。

A, according to the layout, the color steel sandwich wall must be corrected, the corner and corner of wall parasol sealed with aluminum angle, the plates are connected by connecting the I-shaped aluminum, the wall shall be vertical, sealing depth consistent, clean and neat, the wall should be clean, uniform color, neat seams, the diameter of rivet 5X13 @ 300, nail face to be consistent, not scattered, necessary part of the self tapping bolt.


b、按设计图纸标明门窗位置,用切割机割出门窗洞位置,按照门窗洞位置安装窗门,窗为塑钢窗,门卫割下的夹芯彩钢门,进行底层的吊顶,吊顶材料为PVC扣板。

B, according to the design drawings indicate the location of doors and windows, with a cutting machine cut out the window position, in accordance with the window hole for installing windows, window window, the cut sandwich color steel door, bottom ceiling, ceiling material for PVC plate.


走进劳宇
公司简介
企业文化
企业风采
荣誉资质
劳宇产品
集装箱移动板房
活动板房
连体办公房
移动仓储
移动宿舍
移动岗亭
移动卫生间
劳宇案例
合作案例
经典案例
新闻资讯
公司新闻
行业新闻
行业百科
招商加盟
加盟优势
加盟条件

浙公网安备 33011002011924号

友情链接:幸运飞艇开奖直播  pk10官网  pk10开奖直播  皇冠彩票  幸运飞艇  幸运飞艇  pk10官网  

免责声明: 本站资料及图片来源互联网文章,本网不承担任何由内容信息所引起的争议和法律责任。所有作品版权归原创作者所有,与本站立场无关,如用户分享不慎侵犯了您的权益,请联系我们告知,我们将做删除处理!